Residential Services

Residential Permitting & Entitlements in the Phoenix Metro

Every Valley jurisdiction reviews residential work differently, and the differences are large enough to change your schedule by months. This page sets out what each city actually publishes — including which Phoenix fast-track program applies to a house and which one does not.

Discuss Your Permit Path Screen a Parcel First

The short answer

E-Project produces the permit set and manages the submittal — but the useful thing to know before you start is which review path your project will land on. Small remodels often qualify for expedited paths. Hillside parcels almost always disqualify from them. And in Phoenix specifically, the fast track for a house is Priority Expedited Plan Review, not Self-Certification.

Correcting a Common Assumption

Phoenix: Self-Certification vs. Priority Expedited Plan Review

Self-Certification

Not available for a detached single-family house

  • Registered professionals certify code compliance instead of traditional City plan review. Running since 2010.
  • Certifying professional must be an architect or structural engineer registered in Arizona for at least three years, with City training completed and renewed every three years.
  • Residential reach is limited to single-family subdivisions up to 160 acres for grading and drainage civil plans, plus multifamily and other building types — not detached single-family building plans.
  • Explicitly ineligible: hillside development areas, FEMA special floodplain hazard areas, new high-rises, extra-large assembly and hazardous occupancies.
  • City states permits can be issued within one to five business days for eligible projects.

Priority Expedited Plan Review (PEPR)

This is the residential fast track

  • Eligibility explicitly includes non-hillside single family residences when resources are available.
  • Also covers affordable housing, economic development, historic preservation, hospitals, schools and commercial near light rail.
  • Fee: three times the base amount for the plan type submitted, plus 20% of the expedited fee if a third review is needed.
  • Review time: one-half of the published goal for that plan type, with prorated refunds possible if the City misses the deadline.
  • Two caveats: hillside parcels are excluded, and PDD may deny expedited status when staff resources are insufficient.

Sources: Phoenix PDD Self-Certification · Phoenix PDD Priority Expedited Plan Review

Published Targets

What each city says review will take

JurisdictionPlan typePublished target
Phoenix (calendar days, July 2026 report)Custom & standard plansGoal 30 · actual avg 30
Major remodels & additionsGoal 30 · actual avg 37
Minor remodels & additionsGoal 20 · actual avg 24
Plot plansGoal 5 · actual avg 2
Scottsdale (business days)Small Scope Review — residential remodel/addition under 500 SF1 admin · 5 substantive
Pools, fences, walls, signs5 admin · 5 substantive
All other plan types7 admin · 15 substantive
Paradise Valley (business days)All residential — each review cycleUp to 15, plus 3–5 to process the permit
TempeResidentialNo verifiable published figure — confirm with the permit center

Phoenix republishes its turnaround report monthly and recommends planning around the longer of goal and actual. Note that major and minor remodels and additions were both running over goal in the July 2026 report. Every figure here is an initial review target — each resubmittal cycle adds another.

Before the Permit

Approvals that come first

Paradise Valley — Hillside Building Committee

Mandatory pre-application review for all hillside applications, then one of several review tracks. The Town's guidance is explicit that hillside committee review happens before applying for a permit. New homes, remodels, additions, solar, accessory structures and new pools on hillside parcels all go through it.

Scottsdale — Development Review Minor

Required for exterior changes to attached, condominium and multi-family properties. Detached single-family is exempt: additions or changes to detached single-family residences may submit for construction document plan review without Development Review approval.

Tempe — Planning entitlements

Use permits, variances, development plans and land division approvals run through the Planning Division and bodies including the Development Review Commission, Board of Adjustment and Hearing Officer, submitted through the Tempe Citizen Access portal.

Thresholds Worth Knowing

Where the line falls between "minor" and "full review"

Scottsdale

  • No building permit for interior painting, cabinets, flooring, non-structural work, or re-roofing with the same material.
  • Detached non-habitable structures 200 SF or under with no utilities need no building permit — but still need plan approval from Planning Services staff and must meet setbacks.
  • The Minor SFR Remodel/Addition path covers work under 1,000 SF with no second-floor addition and no basement, plus patio enclosures and garage conversions. Applications expire 180 days after last submittal.
  • Any property zoned ESL must be submitted for review regardless.

Paradise Valley

  • Building permit required for any structure over 8 inches requiring a fixed ground location — and a separate application per structure type.
  • Demolition permit required whenever more than 12 linear feet of wall or 12 SF of roof or slab is removed, obtained before the building permit issues.
  • Engineer-sealed grading and drainage plan on any single-family home, or where 999 SF or more of impervious area is added, or work value exceeds $500,000.
  • Fire sprinklers in all new structures, and in existing structures undergoing a 50% addition, alteration or repair.
  • Permits valid 180 days; an inspection must be requested and passed every 180 days.

Requirements and thresholds change. These are cited from each jurisdiction's published materials as of 2026 to illustrate how different the regimes are — E-Project confirms current requirements for your parcel before design begins.

What to Have Ready

Before design starts

  1. Address or parcel number — so zoning district and any overlay can be confirmed first.
  2. Current survey if one exists, or budget for one. On sloped parcels a slope analysis will be needed.
  3. Existing drawings for any remodel or addition; if none exist, plan for existing-condition documentation.
  4. HOA or design review requirements, which are separate from and additional to city review.
  5. Budget range and timeline, including anything driving the date.
  6. Utility and septic information where applicable, particularly on larger or outlying parcels.

Book a Meeting

Related

Frequently Asked Questions

Can an architect self-certify a house in Phoenix?

Not a detached single-family house. The City of Phoenix Self-Certification program has run since 2010 and does allow registered professionals to certify code compliance in place of traditional City plan review, but detached single-family residential building plans are excluded from building plan eligibility; the program's residential reach is single-family subdivisions up to 160 acres for grading and drainage civil plans, plus multifamily and other buildings. To certify building plans a professional must be an architect or structural engineer registered in Arizona for at least three years and complete the City's training, with certification renewing every three years. Projects in hillside development areas and FEMA special floodplain hazard areas are explicitly ineligible.

What is the fastest legitimate way to get a residential permit in Phoenix?

Priority Expedited Plan Review, or PEPR. It is the program that actually applies to single-family work: eligibility includes non-hillside single family residences when resources are available. The fee is three times the base amount for the plan type, and the City states PEPR review times shall be one-half of the published goal for that plan type, with prorated refunds possible if the City misses the deadline. Two caveats matter: hillside parcels are excluded, and the City may deny expedited status even to qualifying projects when staff resources are insufficient.

How long does residential plan review take in the Phoenix area?

Phoenix publishes a monthly turnaround report. In the July 2026 edition the goals were 30 calendar days for custom and standard plans, 30 for major remodels and additions, 20 for minor remodels and additions, and 5 for plot plans — with actual averages running at 30, 37, 24 and 2 respectively. Scottsdale publishes business-day targets: 5 days substantive for residential remodels and additions under 500 square feet, and 15 days for other plan types. Paradise Valley states initial and each subsequent review may take up to 15 business days plus 3 to 5 business days to process the permit. Tempe does not publish a verifiable residential turnaround figure — ask the permit center directly.

What do I need before design starts?

The address or parcel number, so zoning district and overlays can be confirmed. A current survey if one exists. Any existing drawings for a remodel. Your budget range and timeline. For hillside or sloped parcels, expect a slope analysis and an engineer-sealed grading and drainage plan to be required — thresholds vary, and in Paradise Valley a grading and drainage plan sealed by a registered civil engineer is required on any single-family home, or where 999 square feet or more of impervious area is added, or where work value exceeds $500,000.

Does E-Project handle the permit submittal itself?

Yes. Permitting services and entitlement process management are core E-Project services — submittal, comment responses, resubmittal and coordination with the reviewing departments, in addition to producing the drawings. What varies by jurisdiction is which pre-permit approvals are required first, such as Paradise Valley's Hillside Building Committee review or Scottsdale's Development Review Minor for attached, condominium and multi-family exterior changes.

Want the permit path mapped before you commit?

Tell us the address and the scope. We will tell you which review path applies and what it realistically takes.

Book a Consultation Discuss a Project